NASA EXPENDABLE LAUNCH VEHICLE STATUS REPORT (ELV-010507)
NASA via BBSNews - 2007-01-05 -- At the Astrotech payload processing facility near Kennedy Space Center, fueling of the THEMIS spacecraft is under way this week. The probes will be installed onto the payload carrier Jan. 9 to 11. Spin-balance testing will follow Jan. 15 and 16. Mating to the upper stage booster is scheduled for Jan. 26. THEMIS will go to Pad 17-B for mating with the Delta II on Feb. 2.
At Pad 17-B, the first stage of the Delta II rocket is scheduled to be installed into the launcher on Saturday. The nine solid rocket boosters will be placed around the base of the first stage and attached in sets of three between Jan. 8 to 13. The second stage will be hoisted atop the first stage on Jan. 16. The following day, the payload fairing will be lifted inside the clean-room facility located within the mobile service tower. There are no significant issues or concerns at this time. Previous status reports are available on the Web at: Previous Status Reports.
###
|
||||